Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Planner / Construction Scheduler

Project Planner / Construction Scheduler, PT Freeport Indonesia, Deep Ore Zone 2nd Crusher

START Date: 
October, 2005
END Date: 
May, 2007

A brown field construction project for gyratory crusher installation at underground mining area as primary crusher to upgrade DOZ mining production from 35,000 metric tons per day to 50,000 metric tons per day.

As dedicated project Scheduler, responsible to provide detailing EPCC schedule, manpower & equipment resource planning. Representative of Project Control Department during project communication among Underground operation as client, Construction department as execution and CS engineering as drawing design provider.

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
150

Project Planner / Construction Scheduler, PT Freeport Indonesia, Crusher Master Plant

START Date: 
April, 2007
END Date: 
May, 2008

A brown field project of upgrading heavy mills plan to increase grinding capacity of crushing and screening plan to 75,000 metric ton per day. Its include upgrade 5 units wet screens, upgrade 19 units bulk material conveyors and 2 units new conveyors, 2 units new Metso MP-1000 crushers and Crusher building modification.

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
600
Experience Hours (Forensic Analysis): 
300

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content