Planning Engineer / Quality Control Engineer / Quantity Surveyor

Planning Engineer / Quality Control Engineer / Quantity Surveyor, Cementos Pacasmayo , Cement Plant Expantion, civil & concrete service

START Date: 
June, 2006
END Date: 
December, 2010
Cost Control, Planner, Project Control, QA/QC chief in diferent civil works, Plant Expansion.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
2000

Planning Engineer / Quality Control Engineer / Quantity Surveyor, Cementos Pacasmayo , Cement Plant Expantion, civil & concrete service

START Date: 
June, 2006
END Date: 
December, 2010
Cost Control, Planner, Project Control, QA/QC chief in diferent civil works, Plant Expansion.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
2000

Planning Engineer / Quality Control Engineer / Quantity Surveyor, DM Consunji Inc., Intermed Corporate Center / PNCO Housing Project

START Date: 
February, 2005
END Date: 
October, 2006

D. M. Consunji Inc.
2218 DMCI Plaza Chino Roces Extn.
Makati, Metro Manila

Duties          :     ●Administered quality and quantity inspections as regard to concrete
mixture and reinforcing bars and witnessed the testing of materials to ensure results were in compliance with the specification requirements.
●Coordinated with the structural designers and subcontractors details affected by other items as construction work progresses.