Posted Mon, 2009-08-10 10:48 by Gugan Balakrishnan
ยท Typically carried out with a 3 man gang, bedded in cement and sand base |
Floor Areas
Small areas |
much cutting |
0.8 m2/hr |
Large areas |
little cutting |
2.2 m2/hr |
Window Cills etc
Fixing, level line edge batten |
55.5 m/hr |
Fixing tiles, clean and grout |
1.56 m2/hr |