Posted Mon, 2009-08-10 10:48 by Gugan Balakrishnan
· Typically carried out with a 3 man gang, bedded in cement and sand base
|
Floor Areas
Small areas
|
much cutting
|
0.8 m2/hr
|
Large areas
|
little cutting
|
2.2 m2/hr
|
Window Cills etc
Fixing, level line edge batten
|
55.5 m/hr
|
Fixing tiles, clean and grout
|
1.56 m2/hr
|