Rates include for making, fixing, cleaning and minor repair works etc, rates in m2/hr.

Soffits - On runners and props, including erection of props etc.

Hight of Beam Soffit--->      0 - 3.5 m 3.5 - 5.0 m
Width Fix Strike Fix Strike
         
100 - 200 mm 0.70 1.23 0.58 1.02
200 - 300 mm 0.81 1.39 0.68 1.15
300 - 500 mm 0.93 1.54 0.78 1.28
500 - 750 mm 1.16 1.85 0.96 1.54
exc 750 mm 1.23 2.17 1.03 1.82

Soffits - On runners and props, on previously erected props etc.   

Hight of Beam Soffit--->    0 - 3.5 m   3.5 - 5.0 m
Width Fix Strike Fix Strike
100 - 200 mm 0.96 1.69 0.91 1.67
200 - 300 mm 1.11 1.92 1.05 1.82
300 - 500 mm 1.27 2.08 1.20 2.00
500 - 750 mm 1.56 2.50 1.49 2.44
exc 750 mm 1.64 2.86 1.39 2.70

 

Sides - Strutted from soffit bearers etc.

         

Hight of Beam Soffit--->    0 - 3.5 m   3.5 - 5.0 m
Depth Fix Strike Fix Strike
100 - 200 mm 0.78 1.23 0.74 1.18
200 - 300 mm 0.93 1.39 0.88 1.32
300 - 500 mm 1.06 1.54 1.02 1.47
500 - 750 mm 1.47 2.08 1.39 2.00
exc 750 mm 1.54 2.33 1.47 2.33

Sides - Using clamps and struts etc. 

Hight of Beam Soffit--->    0 - 3.5 m   3.5 - 5.0 m
Depth Fix Strike Fix Strike
100 - 200 mm 0.91 1.47 0.87 1.39
200 - 300 mm 1.09 1.64 1.04 1.56
300 - 500 mm 1.27 1.82 1.20 1.72