A relationship between two activities where the Successor activity (the second activity) cannot finish until the Predecessor activity (the first activity) has started. This is essentially an illogical Dependency as it implies time running backwards, however, it is sometimes used to schedule the successor activity 'as late as possible' in relation to the predecessor activity.