Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Revision of Schedule Levels from Wed, 2011-07-13 04:45

Schedule Levels...

When producing programmes for a project, I use the following levels of programmes:

  • LEVEL 1 : Project Management overview schedule/programme, by Project Phase.
  • LEVEL 2 : Area or Process/Utility Unit schedule/programme, by Project Phase by Area or Unit.
  • LEVEL 3 : Discipline schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines.
  • LEVEL 4 : Main Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Main Activities.
  • LEVEL 5 : Detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Detail Activities.
  • LEVEL 6 : Micro-detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Micro-detail Activities.

One School of Thought:

Level 1 to 5 should have a standard definition.
My definition of level 1 - 4 is as follows:

  1. Level 1 - Whole Project
  2. Level 2 - Section or Zone ie Block A Block B etc
  3. Level 3 - Task Summary
  4. Level 4 - Task - which is where the logic is applied

Many planners place logic at level 3 using SS FF links with lags to create overlaps.This is bad planning practice because you do not get a dynamic and resposive critical path.

Another School of Thought:

I use is something along these lines.

  1. Level 1 - The Project
  2. Level 2 - Discipline
    1. Level 2 1. Site Prep, 2.2 Earthworks etc etc
  3. Level 3 - Area / location
  4. Level 3.1 CH 0-300 3.2 CH 300-600

I then use activity coding if I want to see all the works for CH0-300 etc

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.