When producing programmes for a project, I use the following levels of programmes:

  • LEVEL 1 : Project Management overview schedule/programme, by Project Phase.
  • LEVEL 2 : Area or Process/Utility Unit schedule/programme, by Project Phase by Area or Unit.
  • LEVEL 3 : Discipline schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines.
  • LEVEL 4 : Main Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Main Activities.
  • LEVEL 5 : Detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Detail Activities.
  • LEVEL 6 : Micro-detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Micro-detail Activities.