Revision of Schedule Levels from Sat, 2009-03-07 17:30
Schedule Levels...
When producing programmes for a project, I use the following levels of programmes:
- LEVEL 1 : Project Management overview schedule/programme, by Project Phase.
- LEVEL 2 : Area or Process/Utility Unit schedule/programme, by Project Phase by Area or Unit.
- LEVEL 3 : Discipline schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines.
- LEVEL 4 : Main Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Main Activities.
- LEVEL 5 : Detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Detail Activities.
- LEVEL 6 : Micro-detail Activities schedule/programme, by Project Phase by Area/Unit by Single or Multi-disciplines by Micro-detail Activities.