Senior Project Engineer/Functional Project Manager, Eramet France, Hydrometallurgy Processing Plant

START Date: 
January, 2007
END Date: 
December, 2015

Work Experiences

1.                Company                     : WBN-ERAMET FRANCE, year 2007-2015

 

Assignment as Project Manager

 

a)      Projectsexecution and management at site Halmahera North Maluku Indonesia:

-        Support facilities during exploration stage [airstrip and upgrading base campwith utilities, temporaryjetty and access roads for mining pits or exploration drilling areas]. 

-        Complex site geotechnical investigations on shore and off shore areas [Site tests: SPT, CPT-U, Menard Pressuremeter, Trial Earthwork, Geophysic and Lab.tests]. 

-        Site marine data observation [tide, wave and current] and bathymetric survey.

-        Project execution and management for Corporate Social Responsibility [CSR].

 

b)     Detailed Design with Local Consultant for airstrip facility including Construction Permit to Directorate General of Civil Aviation [DGCA] and mine access roads at North part of COW.

 

c)      Bid management including preparation, implementation and analysis of project packages.

 

Assignment as Design Team and Bid Package Coordinator

 

a)      Member of Weda Bay Nickel Project Design and Management Team for Detailed Design Consultancy stageof Hydrometallurgy Process Plant Facilitieswith Technip Geo Production Kuala Lumpur, Egis Franceand Mecater France.

 

b)     Coordinator for bid working packages of BFS Stage

 

2.                Company                     : INDOTECH INDONESIA, year 2002-2004

 

Assignment as Cost Control & Contract Manager

 

Indotech constructed 600 locations of Base Transceiver Station [BTS] Outdoor and 500 locations of Receiver Indoor Stations at Jabodetabek, West Java & Kalimantanareas for Telkomsel Indonesia [Telkomsel Installation Network Facilities or TINEM Project].The scope of work included Site Acquisition Permit [SITAC], civil construction, mechanical electrical installation and power connection with commissioning.

 

This assignment also required to create and implement project control systemin company offices and report directly to the Director.   

 

 

3.                Company                     : BAM DECORIENT INDONESIA, year 1999-2001,

  2005-2006

 

As project staff with responsibility for cost and contract management execution following Company Standard procedures. Assist Project Manager for composing Project Monthly Report as a synthesis of project status, relevant with target profit based on cost forecast analysis and contract simulation.

 

Assignment in several projects corresponds with the above responsibilities:

a)      Cost Control Engineerof Rehabilitation Philip Morris Factory-Marlboro Cigarette Project Karanglo Malang East Java, Indonesia.

b)     Cost Control Engineerof Expansion Nestle Factory Phase II Project Kejayan Pasuruan East Java, Indonesia.

c)      Contract Engineerof San Miguel Food & Beverage Factory Project MM2100 Industrial Area Cibitung West Java, Indonesia.

d)     Contract Engineerof 5 StarsApartment “The Summit” Summarecon Project Kelapa Gading Jakarta, Indonesia.

 

 

4.                Company                     : HUTAMA KARYA INDONESIA, year 1996-1998

 

Main responsible is construction management for tollway projects facilities [underpass-tunnels, bridges-overpass or flyover, retaining walls, tollgates, pavements, drainages include support utilities] based on target budget and schedule. According toCompany Standardprocedure, Construction Manager also as the Alternate of Project Manager for coordination with the Client.

 

Assignment in several projects corresponds with the above responsibilities:

a)      Construction Managerof Tollway Jakarta Outer Ring Road JORR Project Section E1-1 TMII Junction, Indonesia.

b)     Construction Managerof Overpass Bridge Crossing Tollway Road Jakarta–Merak Project at KM 19 Bumi Serpong Damai BSD, Indonesia.

c)      Construction Managerof Tollway Jakarta Outer Ring Road JORR Project Section E1-2 TMII-Ceger, Indonesia.

d)     Project Engineerof Tollway Jakarta Outer Ring Road JORR Project Section S Pondok Pinang-TMII, Indonesia.

 

 

5.                Company                     : PEMBANGUNAN PERUMAHAN INDONESIA,

  year 1995

 

Assignment as Project Engineerat Sol Elite Marbella Apartment Project Cilegon Banten Indonesia.

 

Responsible forfield or site engineering such as shop drawing, workschedule, method statement, design for temporary structure such as formwork, lifting work, temporary drainage, access roads, piling, bar bending and site supervision