Project Engineer, J.F. Shea Construction, Valencia Water Reclamation Plant

START Date: 
December, 2000
END Date: 
December, 2002

Valencia Water Reclamation Plant, Stage Five. Worked as a Project Engineer constructing the $40M water treatment plant expansion for LA County Sanitation. Developed and maintained construction cost and resource loaded baseline schedule comprising over 5,000 schedule activities. Prepared monthly schedule submittals and progress payment requests. Defined contract scopes for both subcontract and purchase orders, managed subcontractors and vendors, processed submittals and requests for information, compiled change order proposals and time extension requests, issued subcontract and purchase order change orders and backcharges. Expedited material and equipment delivery from vendors.

Experience Hours (Planning & Scheduling): 
4100
Experience Hours (Cost Management): 
4100
Experience Hours (Forensic Analysis): 
2100