Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Planner, Beerenberg Corp., Architect

START Date: 
September, 2012

Project Planner:

  • Creating/establishing new project plans and portfolio for the Architect (interior & Fitting)department
  • Running a Baseline revision for annual program including workpackages for area maintenance (Surface  6 Scaffoliding diciplines)
  • Responsible to analize all critical activitites due to variation orders.
  • Status reporting internal & external
  • Responsible to keep the plans updated and accurately, using Safran Project 3.7 version as planning tool.
  • Coorperation with Engineering due to work packages and variation orders.
  • Included in team working to update the process development for planning in Maintenance & Modification projects.

 

Experience Hours (Planning & Scheduling): 
2600