Construction Project Planner / Senior Planner, GE Transportation, FMG Rail Upgrade

START Date: 
October, 2012
END Date: 
October, 2013

Planner, GE Transportation

Project – FMG T155 Rail Mainline Upgrade

„  As the Project planner I was responsible  for rebuilding the master schedule to FMG requirements for the remaining of the $120M project

  • „  Project consists of 150 signalling & communications locations along 290 kms of rail between the Port of Port Hedland and Christmas Creek mine.
  • „  Weekly production of S Curves, IFC & FAT matrixes, Level 2 Summary Schedule and three week look ahead for the client.
  • „  Fortnightly site visits to Port Hedland for client meetings and data gathering for the site construction teams and 3 week swings for commissioning periods.
  • „  Monthly Project Status presentations to senior management of GE Transportation.
  • „  Assisting in a $20 Million claim for delays