Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Scheduling and Controls , JOHARKO International - contracted to Xstrata Copper, Tampakan Copper Project - Prefeasability , Philippines

START Date: 
January, 2006
END Date: 
January, 2008

Establishing effective Project Controls – including systems, processes, procedures and approvals for project based scheduling, document and cost control;

Developing project schedules, utilising Primavera Project Manager Version 5;

Monitoring, progressing and reporting project status to key stakeholders;

Developing detailed project documentation – utilising existing templates, processes and procedures or where necessary creating appropriately structured documents for quality control and tracking of project internal workings together with outputs and deliverables;

Key Stakeholder identification – defining organisational and project structures including roles, responsibilities and levels of authorisation / approval and delegation;

Extensive stakeholder and client liaison at all levels from external service providers, project team members to Project Managers, senior executives and board members.