Project Planner, PJ Hegarty & Sons, Cork, Ireland, The Elysian Development

START Date: 
April, 2006
END Date: 
January, 2008

The Elysian Development, Cork (€125m)includes a 17 storey residential tower, which is currently Irelands tallest building, plus other Residential (211 apartments total), Commercial and Retail.  The development also includes a 2 storey underground car park.  The development is located on a brown field, tidal site and included post-tensioning in the basement design.  My involvement in this project was from the start of Post Contract through to Handover.

 

Responsibilities: PlanningManager services provided include:

  • Master Plan Development, Implementation and Monitoring
  • Financial Forecasting
  • Resource Analysis and Ongoing Assessment
  • Procurement Management of Sub-Contractors
  • Due Diligence
  • Value Engineering workshops
  • Risk Management workshops
  • Coordination of On Site Activities on a daily basis
  • Coordination and control of information requirements
  • Coordination and control of material orders and deliveries