Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Project Planning Engineer, J M Murphy, North West Operational Property Framework Agreement

START Date: 
March, 2008
END Date: 
March, 2009

Worked on the LNW Operational Property & Infrastructure Framework based in the North West. 

Day to day tasks included production, costing, resourcing & updating of both tender & live programmes in P3e for all work on the framework ranging from simple resurfacing works on a footbridge to major reconstruction works of lineside properties (Depot, Signal Boxes, Stations etc). 

This was done from interrogating & rationalizing into a workable programme using Form’s A, B & AFC’s, Remits, Pricing Documents, PMI’s and any other information to hand. 

I liaised with the client, project managers, QS’s and anyone else who may have an input involved in the day to day running of the project to ensure milestones are met and the projects are running on time & to budget. To ensure any major slippages are caught early and dealt with and to have a proactive approach to the programming of works ensuring the programmes are not only realistic but also achievable 

Production of weekly, bi-weekls & monthly reports in line with internal & client requirements.