Planning Manager, Penta - Ocean, Matarbari Urgent Super Critical Coal Fired Power Station

START Date: 
October, 2017

Planning Manager for $1.7Bn Preparatory Works for Power Station in Bangladesh. Encompassing dredging, civil works, reclamation, construction. Liaising with client, project managers, sub-contractors to ensure full interfacing.

             Developed Master Baseline Schedule, fully cost/resource loaded

             Managing and co-ordination of 2 staff

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500