Planning Engineer / Project Scheduler, Hanjin Heavy Ind. /Sumitomo-MHI. Philippines, Davao International Airport Development Project; Manila Light Rail Transit - Depot Project

START Date: 
May, 2000
END Date: 
March, 2002

 

  • Develop project schedule for the execution of work covering schedule, manpower and progress, utilizing Primavera (P3).
  • Give input to and review subcontractors – plans to ensure logic and interfaces with project planning.
  • Physical and financial progress monitoring and review of all trades of works, and report deviations.
  • Monitor forecast schedule and initiate actions when this schedule deviates from current plan.
  • Prepare baseline revisions to catch up the schedule.
  • Prepare internal and external project reports and follow up sub-contractors planning and progress reporting. 
Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
3500
Experience Hours (Forensic Analysis): 
3500