Senior Planning Engineer / Cost Control, STANLEY (USA), JASSIM QABAZARD (Kuwait) AND AIRWAYS (new Zealand)(JOINT VENTURE) CONSULTANTS, KUWAIT AIRSPACE SYSTEM PLAN (KASP)
KUWAIT AIRSPACE SYSTEM PLAN (KASP) including subproject as: 1- Kuwaitcontrol & metrological center 2- Electrical Infrastructure &South Power Building Project 3- Communication System Project 4- Air Traffic Management System Project 5- Surface Movement Radar Project 6- Airport Surveillance Radar Project 7- Instrument Landing System Project 8- KuwaitAirportData Interchange Network |
Consultancy For The Project Management And Supervision Of Works Involved In The Implementation Of The Kuwait Airspace System Plan At Kuwait International Airport |
Senior Planning Engineer / Cost Control |
234,300,283 KD , 937,200,000 $ |
Creating, following up &updating KASP overall program & overall monthly report, tentative schedule for projects under tendering. Detecting delays in each subproject and to the overall, Review each subproject CPM program, analyses critical path for each subproject after/before updates, Cost loading, Resource loading, Method of Statement, Payments, Variations, Monthly Reports submitted by contractor. Monitor the progress at site. Attending & participate at progress meetings. Review and validate extension of time claims submitted by contractors. Analysis all delays in the KASP project and Subprojects.
|