VP of Primavera solution consulting and implementation, Shanghai Power, Changxin Thermal Power Plant, China Petroleum Engineering Co., Ltd. EPM, Ltd. Northeast Branch EPM, Shenzhen Mobile Communication Co.

START Date: 
June, 2001
END Date: 
February, 2007
  • Responsible for Enterprise Project and Program Management Solution presale and implementation.
  • The sole author of Chinese Primavera product Reference Manuals and Training materials.
  • Primavera Products and Localization Manager,Responsible for all localization work of all Primavera products and training.
  • Project Manager, Responsible for implementation and integration service of Enterprise Project Management Solution for Shenzhen Mobile Communication Co., Ltd.
  • Project Manager,  Responsible for Primavera product implementation  service  for Electric Power of Hennan Province.
  • Project Manager,  Responsible for Primavera product implementation  service for China Petroleum Engineering Co., Ltd. Northeast Branch.
  • Consultant,Responsible for consulting service of Enterprise Project Management Solution for China Tianchen Chemical Engineering Corporation.
  • Project Manager,  Responsible for Primavera product implementation service for Electric Power of Jiangsu Province.
  • Consultant,  Responsible for Primavera product implementation  service for Changxin Thermal Power Station in Zhejiang Province.
  • Project Manager,  Responsible for Primavera product implementation service for Zhejiang Thermal Power Construction Company.
  • Project Manager,  Responsible for Primavera product implementation service for QinbeiThermal Power Station Project in Hennan Province.
  • Project Manager,  Responsible for Primavera product implementation service for Beijing ABB Co. Ltd.
  • Project Manager,  Responsible for Primavera product implementation service for Shanghai Voith Siemens.
  • Project Manager,  Responsible for Primavera product implementation service for Puyang Transformer Substation Project in Hennan Province.
  • Consultant,  Responsible for Primavera product implementation service for ShuoHuang Railway Project.
Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
1400