VP of Primavera solution consulting and implementation, Shanghai Power, Changxin Thermal Power Plant, China Petroleum Engineering Co., Ltd. EPM, Ltd. Northeast Branch EPM, Shenzhen Mobile Communication Co.
START Date:
June, 2001
END Date:
February, 2007 - Responsible for Enterprise Project and Program Management Solution presale and implementation.
- The sole author of Chinese Primavera product Reference Manuals and Training materials.
- Primavera Products and Localization Manager,Responsible for all localization work of all Primavera products and training.
- Project Manager, Responsible for implementation and integration service of Enterprise Project Management Solution for Shenzhen Mobile Communication Co., Ltd.
- Project Manager, Responsible for Primavera product implementation service for Electric Power of Hennan Province.
- Project Manager, Responsible for Primavera product implementation service for China Petroleum Engineering Co., Ltd. Northeast Branch.
- Consultant,Responsible for consulting service of Enterprise Project Management Solution for China Tianchen Chemical Engineering Corporation.
- Project Manager, Responsible for Primavera product implementation service for Electric Power of Jiangsu Province.
- Consultant, Responsible for Primavera product implementation service for Changxin Thermal Power Station in Zhejiang Province.
- Project Manager, Responsible for Primavera product implementation service for Zhejiang Thermal Power Construction Company.
- Project Manager, Responsible for Primavera product implementation service for QinbeiThermal Power Station Project in Hennan Province.
- Project Manager, Responsible for Primavera product implementation service for Beijing ABB Co. Ltd.
- Project Manager, Responsible for Primavera product implementation service for Shanghai Voith Siemens.
- Project Manager, Responsible for Primavera product implementation service for Puyang Transformer Substation Project in Hennan Province.
- Consultant, Responsible for Primavera product implementation service for ShuoHuang Railway Project.
Experience Hours (Planning & Scheduling):
3500
Experience Hours (Cost Management):
2500
Experience Hours (Forensic Analysis):
1400 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: