Sonia Collins BSc (Hons) Pg Dip MCIOB
Preconstruction Stage:
· Production of feasibility and tender programmes.
· Fully logic linked design, procurement and construction programmes.
· Outline Method Statements and Logistics Diagrams.
· Peer Review / Audit of preconstruction programmes.
Construction Stage:
· Compilation of Target and Contact programmes (JCT Contract)
· Compilation of accepted programme (NEC Contract)
· Package and procurement programmes for each element of the works.
· Maintenance of programme, progress, forecasts and asbuilt.
· Critical Path Analysis / Forensic Planning.
· Earned Value Analysis.
· Peer Review / Audit of Construction Stage Programmes, Progress and Forecasts.
· Programme Risk Reviews, identifying, monitoring and reporting, together with risk mitigation strategies.
Disputes and Claims:
· Impacted as planned
· As planned v as built
· Time impact analysis
· Collapsed as built
· Retrospective extension of time claim preparation.
· Extension of time claim auditing and appraisal.
· Retrospective preparation of as built programme.
Training Courses
Bespoke planning training courses developed with you for your specific needs.
Examples of some delivered to date:
· Understanding the operation of the programme in NEC contracts
· Basic planning skills for site managers
· More advanced planning skills for project managers
· 1 day planning awareness for graduates.
Planning / Project Controls Strategy
Are the progress reports you get from your projects accurate and consistent? Do you have a clear strategy on how you deal with progress reporting, as built records etc on all your projects? If not we can help you develop one.
- Industry: