Responsible for the planning and reporting of the Hawtah to pumping station no. 3 project.
Project comprised the construction of 340km of 24” pipeline, 20 valve stations, and a pig launching and receiving facility.
Responsible for the planning and reporting of the Hawtah to pumping station no. 3 project.
Project comprised the construction of 340km of 24” pipeline, 20 valve stations, and a pig launching and receiving facility.
Links:
[1] http://www.planningplanet.com/category/project/hawtah-pumping-station-number-3-pipieline-project
[2] http://www.planningplanet.com/category/company/mcconnell-dowell-middle-east-ltd
[3] http://www.planningplanet.com/category/industry/oil-gas-power
[4] http://www.planningplanet.com/taxonomy/term/142
[5] http://www.planningplanet.com/category/skills/progress-monitoring
[6] http://www.planningplanet.com/taxonomy/term/14310
[7] http://www.planningplanet.com/taxonomy/term/13025
[8] http://www.planningplanet.com/category/region/middle-east-region/asia/saudi-arabia-assa