Lump sum Qty errors in Variation

No replies
Umer Mehmood
User offline. Last seen 5 years 28 weeks ago. Offline
Joined: 14 Jan 2016
Posts: 8
Groups: None

Dear friends

Please advise about your comments for the below mentioned secnario

Example as per Tender Drawings the Qty of foundation Concrete is 100 cum , while in the BOQ by Mistake its mentioned as 50 cum.

Now there has been changes and qty as per new drawings is  120 cum , 

Please advise what would be the qty considered for variation 

Option #1 -  Using BOQ Qty = 120-50  = 70 Cum

Option # 2 - Unsing Qty as per Tender = 120-100 = 20 cum

Please give your feedback 

Thanks