Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavea 6.2.1 callenders

No replies
Mark Dunn
User offline. Last seen 12 years 40 weeks ago. Offline
Joined: 14 Sep 2010
Posts: 8
Groups: None

I have a schedule with a base callender of 8hrs per day.  when I add activities and give them a specific callender of 24 hrs per day I have to enrter 3 days into the duration column to get 1 day between the early start/early finish dates.  Does anyone have any idea how to solve this?  Thanks, Mark