Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Recording Actual Units in P6

No replies
aqil mahmood
User offline. Last seen 8 years 22 weeks ago. Offline
Joined: 19 Aug 2005
Posts: 18
Groups: None

Hi Guys

 

Is it possible to record actual unit rates in P6,

lets take an example of concrete

fora an activity Budgeted unit rate of concrete assigned in Baseline is 500 dollars per m3 and total quantity is 200 m3

then from site we got the report that actaully we purchased concrete at 450 dollars and 202 m3 concrete is used.

For recording actual quanity in P6 no problem, but where to feed actual unit rate (450 dollars) in P6 so that i can have actual cost for this?

 

Please help

 

Aqil