WBS Weight

No replies
Anu Tor
User offline. Last seen 13 years 12 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
Dear all members,

I created schedule and arranged WBS weight to each WBS. After completed assigned WBS to each activities, then schedule has been updated.

No any effect from WBS weight to schedule progress.

Please advise the correct action to use WBS weight.

Thanks,