P3e/ SAP interface - EVM

No replies
Robert Mellalieu
User offline. Last seen 4 years 47 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 16
Groups: None
I accept the fact that there is such an interface (Impress). What
I am after is anyone with advice with respect to the above. Planning for planning if you like!
I am also interested in any advice/ recommendations when applying EVM to a Prime Contract? There’s a lot of data out there, has anyone done it with P3e?
Cheers
Rob