Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

what is standard for creating any equipment house schedule

No replies
Kumar Baiju
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi all

   I want to create a schedule for compressor House  in which there is five same type of compressor, gear box, motor, silenser, mist eliminator, lub oil system, Motor cooling hydraulic system exist.

according to me

Process : 1. Craete PFD & PID

Equipment : 1. compressor, base plate, silecer, mist eliminator PDS (process data sheet) .EOT Crane

            2. Technacil spec for same

               3. detailing for same

Electrical

      Load list

cable rack, cable schedule, cable trench, detailing

Instrument

      Instrument data sheet for Control valve, other instrumnet,

      Technical specification for instrument, Control cale scheduling, cable trench

Piping

       Piping layout, piping Isometric

 Structural

    Compressor house shed

    detail for EOT crane Support

    Combined load data (static & dynamic) for civil drawing

Civil

   Piping layout, Foundation detail, Foundation bolt detail.

 

i have give some measure activity can any one give the detail of the schedule.

 

Regards\\