START Date:
January, 2005
END Date:
November, 2006 Severn Trent WID (Planning Engineer / Project Controls Engineer)2005 - 2006
Upgrading of three Sewage Sludge Incinerators to Waste Incineration Directive compliance. Main works undertaken during 6 pre-planned shut downs of 4 weeks duration each. Detailed planning and resource control during shut downs involved, which required planning each working hour of each shut down day. Contract completed on time and on budget
Planning Software Used - Primavera P3
Upgrading of three Sewage Sludge Incinerators to Waste Incineration Directive compliance. Main works undertaken during 6 pre-planned shut downs of 4 weeks duration each. Detailed planning and resource control during shut downs involved, which required planning each working hour of each shut down day. Contract completed on time and on budget
Planning Software Used - Primavera P3