Douglas WTW (Planning Engineer)                    2006 – 2007
Turnkey Potable Water, 2 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, Manganese Reduction Rapid Gravity Filters, Sludge Press and all Associated Chemical Dosing. Treatment Rate 32 MLD. Project planning from contract award has helped identify time savings such that Contract Completion is 27th February 2008, and Planned Completion is 20th November 2007.

Planning Software - Primavera P3