Network Rail Planning Manager
START Date:
February, 2009
END Date:
June, 2009 WEST COAST NORTH – NETWORK RAIL A09 RESIDUAL PROJECTS & SNAGGING
Planning Manager – 5 Projects; (4 subcontractors – P/Way, M&E, Civils, S&T, OLE) Project Value £60M.
Eden Valley, TV4, Sharp, Primrose Hill, Stafford Panel, Colwich 20/21A/B points- commissioned.
Safely delivered Stoke On Trent Station Remodeling – A complete project life cycle from; tender, approved in principal (AIP), design, procurement, construction testing & commissioning stage 4A2 on budget and on time 01/06/09. (P/Way plain lining, OLE – bases, structures & decommissioning, Heights & Staggers, telecoms reconfiguration, new signal point phones & bases, M&E – location cases and power installation, Civils-station platform extension to accommodate 12 cars, track side civils, Signaling – SSI boundary reconfig, new signal bases, structures & signals including junction indicators & ground signals, signal gantry decommissioning)
Safely delivered Stoke On Trent Station Remodeling –design, procurement, construction testing & commissioning stage 4A1 on budget and on time 26/05/09. (P/Way plain lining, telecoms reconfig, platform extension & signaling)
Planning Manager – 5 Projects; (4 subcontractors – P/Way, M&E, Civils, S&T, OLE) Project Value £60M.
Eden Valley, TV4, Sharp, Primrose Hill, Stafford Panel, Colwich 20/21A/B points- commissioned.
Safely delivered Stoke On Trent Station Remodeling – A complete project life cycle from; tender, approved in principal (AIP), design, procurement, construction testing & commissioning stage 4A2 on budget and on time 01/06/09. (P/Way plain lining, OLE – bases, structures & decommissioning, Heights & Staggers, telecoms reconfiguration, new signal point phones & bases, M&E – location cases and power installation, Civils-station platform extension to accommodate 12 cars, track side civils, Signaling – SSI boundary reconfig, new signal bases, structures & signals including junction indicators & ground signals, signal gantry decommissioning)
Safely delivered Stoke On Trent Station Remodeling –design, procurement, construction testing & commissioning stage 4A1 on budget and on time 26/05/09. (P/Way plain lining, telecoms reconfig, platform extension & signaling)