Impex Development Planner

START Date: 
March, 2006
END Date: 
July, 2008
     Participated in all levels of scheduling, from preparation of master schedules (Level I) to development
of detailed project component schedules (Levels IV and V) for structural, external envelope, internal finishing, roadways, landscaping, acoustics, mechanical, electrical, and plumbing works
     Prepared progress breakdown for all BOQ items and updated the PCT on a weekly basis
     Developed charts and tables that tracks resources needed to achieve project targets
     Prepared the (MRP) material requirements planning and the(MRR) material receiving reports
     Conducted in-dept review and analysis of all submittals from contractors relating to planning and scheduling for payment purposes