Kuk Dong Construction Co.,Ltd. Project Controls Engineer
START Date:
November, 1991
END Date:
June, 1997 1. Preparation for Monthly Progress Payment claim, submission and negotiation.
2. Monitoring sub-contractors applications and payment
3. Preparation of Escalation claim, submission and negotiation.
4. Main material controlling.
5. Scheduling and planning (overall schedule, two months look ahead schedule, two weeks look ahead schedule, CPM).
6. S-curve, manpower and equipment bar chart.
7. Involved in tender team to prepare bid document for tender. Quantity measurement, unit price calculation and analysis based on direct cost (skilled/unskilled labor rate, material, transportation cost from quarry to plant and plant to site, equipment, etc.), indirect cost (manager/supervisor rate, over head, etc.), depreciation, inflation, etc.
2. Monitoring sub-contractors applications and payment
3. Preparation of Escalation claim, submission and negotiation.
4. Main material controlling.
5. Scheduling and planning (overall schedule, two months look ahead schedule, two weeks look ahead schedule, CPM).
6. S-curve, manpower and equipment bar chart.
7. Involved in tender team to prepare bid document for tender. Quantity measurement, unit price calculation and analysis based on direct cost (skilled/unskilled labor rate, material, transportation cost from quarry to plant and plant to site, equipment, etc.), indirect cost (manager/supervisor rate, over head, etc.), depreciation, inflation, etc.
- Industry:
- Region: