START Date:
April, 1986
END Date:
November, 1989 Precious Metal Refinery:
As Assistant Planner:
Setting up a computerised network programme from manual drawn networks. Compiling & maintaining a mechanical equipment list.
Obtaining information from Procurement & Expediting.
Producing manhour āSā Curve reports.
As Planner:
Transferred to site. Maintaining site programme, producing various multi-discipline and management reports. Attending progress meetings for construction & commissioning.
As Assistant Planner:
Setting up a computerised network programme from manual drawn networks. Compiling & maintaining a mechanical equipment list.
Obtaining information from Procurement & Expediting.
Producing manhour āSā Curve reports.
As Planner:
Transferred to site. Maintaining site programme, producing various multi-discipline and management reports. Attending progress meetings for construction & commissioning.
- Industry:
- Region: