Hsin Chong Engineering (Macau) Ltd Senior Planner

START Date: 
August, 2005
END Date: 
November, 2008
•     Approving/disapproving sub-contractors programmes
•     Tracking procurement schedules, compare contractors 3-week rolling programmes with the Master Programme and advised contractors the schedule of areas to work on
•     Conduct daily site inspection for site work progress with photo recording and programme updating.
•     Liaise with other trades and subcontractor for avoid work area conflicts.
•     Prepare S-curves for presentation clarity, prepare and update records for shop drawing and material samples submissions.
•     Planning, recording and reporting the overall progress of numerous work packages. These works involved preparation of construction working schedules of works and presented them to the Client for approvals and further coordination with contractors.
•     Produced detailed works programme and schedules using Primavera P3 and Microsoft Project.
•     Document presentation includes Critical Path Method sequence of works, task dependencies, task conflicts and management of distribution of resources.
•     Prepared all documents and presentations in professional, visually striking manners to show the project progress, forecasting, critical tasks, task conflicts, progress variations and budgetary variations.
For project management role, he managed the coordination and planning aspects of the external façade works at the Venetian Resort Hotel Casino project in Macao. The duties include:
•     Monitor facade design process, procurement processes, and quality control.
•     Prepared written reports to the Clients to inform the overall progress of the façade.
•     Managed the technical aspects of the facade procurement works for items like aluminum curtain walling, Glass Reinforced Concrete (GRC), Glass Reinforced Plastics (GRP), Glass Reinforced Gypsum (GRG), and metal cladding exterior façade works.
•     Sought resolutions to technical issues such as materials defect, delivery, logistics, schedules and site problems.
•     Undertook daily site investigation to accurate record various work progress, material checking and performed basic surveying.