P6 Resource Assignment


6609
capture.jpg
Guys i need help to resolve some difficulties in P6. Please see below example - 

1. I created manpower resource 'Planning Engineer'.

2. assigned a manpower resource to 'Level of Effort' Activity and assigned Budgeted units/Time as 3 nos.

3. when i check this in Resource Assignment window, it shows as 4 units per month, however at activity level it show correct value as 3 units per month.

4. its giving differnt result at Activity level and Resource level (summarized)

Guys your inputs on this mateer will be apriciated.

 

Thanks

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes