Scheduling Roads and Earthmoving Activities

USES OF DRONE APPLICATIONS TO MONITOR PRODUCTIVITY

"USES OF DRONE APPLICATIONS TO MONITOR PRODUCTIVITY" by Piero Anticona

Abstract: Drones are Unmannered Aerial Vehicles (UAV) that are having different applications because of the amount of information that they can collect in a short period of time during flight inspections.

It is also, one of the technologies that are rapidly increasing its use in construction, agriculture, maintenance, building design, mining, solar, etc.

How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture: