MS Project do not provide a tool to highlight a time period in Gantt chart.

So how can we do it?

First you create a new calendar. For example "Gantt Shade"

how-to-highlight-a-time-period-in-gantt-chart-in-microsoft-project-1

In Exception tab, add the Time period you want to highlight. (From January to March)

how-to-highlight-a-time-period-in-gantt-chart-in-microsoft-project-2

Right click on Gantt chart and select Nonworking Time...

how-to-highlight-a-time-period-in-gantt-chart-in-microsoft-project-3

In Non-working time tab, in Calendar select Gantt Shade, in Draw select Behind task bars, in Color select Gray color.

how-to-highlight-a-time-period-in-gantt-chart-in-microsoft-project-4

Now Time period from Jan to Mar has been highlighted.

how-to-highlight-a-time-period-in-gantt-chart-in-microsoft-project-5

 

Thank you for your time to read this article.