ADCTX March 2008 – March 2009
Morsa West Field Development
Dolphin D-111 Rebuild, Transit, Installation, HUC
Angola, Africa
Project Scheduling Lead
Develop and manage overall plan and schedule in P6. Set the schedule activities weighted value, baseline schedule and report progress against the baseline. Integration of drilling, diving / sub-sea and commissioning schedules into the overall master schedule. Additionally, I was responsible for resource loading and P.O.B. forecasting around the constraints of limited bed space in order to achieve first oil in a safe and timely manner.