Schedule Statusing Sheet

"Schedule Statusing Sheet" by Alexander Cartwright

Description: an excel sheet to be used for statusing a project using

  1. Do not edit task data; please see scheduler for task data changes.
  2. Filter for your name in the CAM Column
  3. For tasks that have started, or should have started, enter an Actual Start (Column O) or Forecast Start in (Column Q)
  4. For tasks that have finished, or are forecast to finish, enter an Actual Finish (Column P) or Forecast Finish (Column R)
  5. For All tasks that have started and are not yet finished, determine their percent complete.
  6. Keep in mind it must be equal or greater than the last reporting period