Most Programmes are sperated into high level grops of such as Design, Procurement, Construction, Commissioning etc.
The long lead items sould exist in the Procurement area with lower levels of grouping typically by the procurement work package type, but potentially also by the discipline or location, or responsibile manager etc.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2019-07-17 14:10
Member for
20 years 6 monthsMost Programmes are sperated
Most Programmes are sperated into high level grops of such as Design, Procurement, Construction, Commissioning etc.
The long lead items sould exist in the Procurement area with lower levels of grouping typically by the procurement work package type, but potentially also by the discipline or location, or responsibile manager etc.
Member for
16 years 3 monthsIf you assign them to their
If you assign them to their own wbs it should not matter. At the top should always be milestones because they are the most important thnig.