Titanium Roofing System
Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc.
Titanium roof on multiple sub‑layers.
Typical composite rate of 9.5 m2/day.
Installation
Typical timing and sequence of works. This is for an order of 5,000 m2 (HK Station Upper & Lower Roofs)...
Element
Week
Manpower
Temporary Works
0 - 2
5
Metal Decking
2 - 3
12
Gutter Subframe
3 - 6
6
Vapour Barrier
4 - 13
4
Rockwool
4 – 13
44
Cement Board
4 – 13
6
Ice / Water Shield
4 – 13
4
Gutter Lining
6 - 9
4
Aluminium Cladding / Subframe
6 – 11
6
Titanium Cladding
8 – 17
17
Aluminium Pannelling
9 - 14
6