Opinions regarding the display of long lead items on a programme

Member for

20 years 6 months

Most Programmes are sperated into high level grops of such as Design, Procurement, Construction, Commissioning etc.

The long lead items sould exist in the Procurement area with lower levels of grouping typically by the procurement work package type, but potentially also by the discipline or location, or responsibile manager etc.

Member for

16 years 3 months

If you assign them to their own wbs it should not matter. At the top should always be milestones because they are the most important thnig.