GLOBAL CHANGE - WBS

Member for

21 years

Prasad,

 

I only use two of the twenty % complete fields in layouts:

Performance % complete is Earned Value  (BCWP/BC * 100)

Schedule % complete is Planned Value  (BCWS/BC * 100)

Note that thees are both cost related. If your baseline was created before you made each resource $1.00 per hour, Schedule % complete will not roll up.  You may need to:

Restore the baseline

Reset the resource costs (under the "tools" menu in the windows client)

make it a baseline again

 

Member for

12 years 8 months

Dear David,

Iam greatful to your reply. Thank u somuch.

I will immediatly assign a cost to the units ( @ 1 $/MHr) & I will check. & I hope it will roleup gives me the Plan % at Activity/WBS level also.

But, can u please suggest me that for which Field (Column name) I can see the Rollup % or

If I needs to apply what will be the Global change Formula for the UDF " Plan %" .?

Thanks again.

Prasad

Member for

21 years

Prasad,

My understanding of your query is that you are doing Earned Value Analysis in Manhours, not Money.

That you cannot see summary values suggests you are using P6.

P6 does not do earned value in quantity properly.

You will need to set the value of all resources to $1.00 per hour in both the current and baseline plan.

Then you will see the WBS  values, weighted by cost but with $1.00 per hour, cost=quantity