I only use two of the twenty % complete fields in layouts:
Performance % complete is Earned Value (BCWP/BC * 100)
Schedule % complete is Planned Value (BCWS/BC * 100)
Note that thees are both cost related. If your baseline was created before you made each resource $1.00 per hour, Schedule % complete will not roll up. You may need to:
Restore the baseline
Reset the resource costs (under the "tools" menu in the windows client)
Member for
21 yearsPrasad, I only use two of the
Prasad,
I only use two of the twenty % complete fields in layouts:
Performance % complete is Earned Value (BCWP/BC * 100)
Schedule % complete is Planned Value (BCWS/BC * 100)
Note that thees are both cost related. If your baseline was created before you made each resource $1.00 per hour, Schedule % complete will not roll up. You may need to:
Restore the baseline
Reset the resource costs (under the "tools" menu in the windows client)
make it a baseline again
Member for
12 years 8 monthsDear David, Iam greatful
Dear David,
Iam greatful to your reply. Thank u somuch.
I will immediatly assign a cost to the units ( @ 1 $/MHr) & I will check. & I hope it will roleup gives me the Plan % at Activity/WBS level also.
But, can u please suggest me that for which Field (Column name) I can see the Rollup % or
If I needs to apply what will be the Global change Formula for the UDF " Plan %" .?
Thanks again.
Prasad
Member for
21 yearsPrasad,My understanding of
Prasad,
My understanding of your query is that you are doing Earned Value Analysis in Manhours, not Money.
That you cannot see summary values suggests you are using P6.
P6 does not do earned value in quantity properly.
You will need to set the value of all resources to $1.00 per hour in both the current and baseline plan.
Then you will see the WBS values, weighted by cost but with $1.00 per hour, cost=quantity