Planning, Scheduling & Programming Discussion Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Sat, 2016-02-20 11:02 Permalink The idea is that the baseline The idea is that the baseline shall be scheduled as current status but not statused as actual. Meaning the schedule is planned as current status. Once accepted as baseline then create a copy to update and statuses the activities accordingly. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2016-02-20 08:28 Permalink Hi JordanI take the opposite Hi Jordan I take the opposite view to Patrick. The progress data should reflect what actually happened so it should be added to your "trial" programme. If changes are required to get approval then the new programme is easily progressed a second time. Best regards Mike Testro Member for 24 years 9 months Member for 24 years 9 months Submitted by Patrick Weaver on Sat, 2016-02-20 07:31 Permalink Not a good idea - the Not a good idea - the baseline may be adjusted to reflect what is actually happening but generally the 'baseline' is the planned situation. Log in or register to post comments
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Sat, 2016-02-20 11:02 Permalink The idea is that the baseline The idea is that the baseline shall be scheduled as current status but not statused as actual. Meaning the schedule is planned as current status. Once accepted as baseline then create a copy to update and statuses the activities accordingly.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2016-02-20 08:28 Permalink Hi JordanI take the opposite Hi Jordan I take the opposite view to Patrick. The progress data should reflect what actually happened so it should be added to your "trial" programme. If changes are required to get approval then the new programme is easily progressed a second time. Best regards Mike Testro
Member for 24 years 9 months Member for 24 years 9 months Submitted by Patrick Weaver on Sat, 2016-02-20 07:31 Permalink Not a good idea - the Not a good idea - the baseline may be adjusted to reflect what is actually happening but generally the 'baseline' is the planned situation.
Member for
15 years 11 monthsThe idea is that the baseline
The idea is that the baseline shall be scheduled as current status but not statused as actual. Meaning the schedule is planned as current status. Once accepted as baseline then create a copy to update and statuses the activities accordingly.
Member for
19 years 10 monthsHi JordanI take the opposite
Hi Jordan
I take the opposite view to Patrick.
The progress data should reflect what actually happened so it should be added to your "trial" programme.
If changes are required to get approval then the new programme is easily progressed a second time.
Best regards
Mike Testro
Member for
24 years 9 monthsNot a good idea - the
Not a good idea - the baseline may be adjusted to reflect what is actually happening but generally the 'baseline' is the planned situation.