there are rates at the top of this page for to determine installation durations. There are also standard estimating programs out there that will give you durations based on industry standards of installation i.e. X number of LF of large conduit installtion per day. Timberline (now SAGE), Richardson Race, Accu Bid, McCormik, Cubit, STACk, Turbobid, ProEst.
Ed, Actually there is no such standard production rate, Its depends upon your company status regarding the Maximum number of labors, Machinery and cash.
For example, concrete road surfacing (300mm)-6.7 m2/hour, But the important thing is whether your company can produce exact productivity? or some time your project team have high capacity to produce more?
unbalanced productivity can create problems while setting duration and float.
First of all you need to arrange all the activities with in the contractual dates. from there you have to set the productivity then durations and links . you can consult the construction managers, site engineers, machines like excavator- there is a standard productivity, But the excavation rate depends upon the number of excavation machines own/available from your own company side, here your company former data/historical data plays an important role
i will send you a link for productivity, but use it for just comparison purpose
Member for
16 years 3 monthsthere are rates at the top of
there are rates at the top of this page for to determine installation durations. There are also standard estimating programs out there that will give you durations based on industry standards of installation i.e. X number of LF of large conduit installtion per day. Timberline (now SAGE), Richardson Race, Accu Bid, McCormik, Cubit, STACk, Turbobid, ProEst.
Member for
7 years 7 monthsHello Sir, Could you please
Hello Sir,
Could you please send me too on gaborrazvan24@yahoo.com the file with the productivity rates?
Best Regards,
Razvan Gabor
Member for
8 years 5 monthsDear All,Please send excel
Dear All,
Please send excel file for Manpower productivity for Building & construction projects in UAE,
my email ID, mubarakduke@gmail.com
Thanks,
Mubarak.s
Member for
10 years 1 monthplease reyes if you got the
please reyes if you got the excel sheet on productivity rates please send to my email
donjoel80@yahoo.com
i will appreciate
Member for
10 years 1 monthplease reyes if you got the
please reyes if you got the excel sheet on productivity rates please send to my email
donjoel80@yahoo.com
i will appreciate
Member for
17 years 8 monthsCheck out this
Check out this post
http://www.planningengineer.net/construction-civil-works-productivity-r…
Member for
17 years 5 monthsplease send me production
please send me production rate usuf22@yahoo.com thx
Member for
17 years 4 monthsGood Morning all, Can any
Good Morning all,
Can any one forward the link to my email id ameenpasha@galfarqatar.com.qa , ameen_pasha10@yahoo.com
Thanks in advance.
Member for
19 years 10 monthsHi Mangesh The prices are in
Hi Mangesh
The prices are in £ but the production rates are pretty well universal.
Best regards
Mike Testro
Member for
19 yearsHi ed, could you provide me
Hi ed,
could you provide me with the link for productivity rates as i am in need for one of my project in dubai. my mail karthik2681@rediffmail.com
thanks
Karthik
Member for
14 years 7 monthsHello Mike...Thanks for the
Hello Mike...
Thanks for the info...I'll look for this..regards
Member for
18 years 6 monthsDear Mike, Is the RICS
Dear Mike,
Is the RICS estimating guide only meant for UK region?.
regards,
Mangesh Khuspe
Member for
14 years 6 monthsHello Mr Saju T.S can u
Hello Mr Saju T.S can u forward me a copy / link for productivity
Thank you
Member for
19 years 10 monthsHi Ed The RICS publish
Hi Ed
The RICS publish estimating books - also on CD - which have production outputs for construction work including M&E.
Other publications are Spons and also Hutchinson which you can order from Amazon.
Best regards
Mike Testro
Member for
14 years 11 monthsHi Saju, Can you send me too
Hi Saju,
Can you send me too the link for productivity?
Thank you,
SPP
Member for
14 years 7 monthsthanks for the info.
thanks for the info.
Member for
16 years 4 monthsHiEd, Actually there is no
Hi
Ed, Actually there is no such standard production rate, Its depends upon your company status regarding the Maximum number of labors, Machinery and cash.
For example, concrete road surfacing (300mm)-6.7 m2/hour, But the important thing is whether your company can produce exact productivity? or some time your project team have high capacity to produce more?
unbalanced productivity can create problems while setting duration and float.
First of all you need to arrange all the activities with in the contractual dates. from there you have to set the productivity then durations and links . you can consult the construction managers, site engineers, machines like excavator- there is a standard productivity, But the excavation rate depends upon the number of excavation machines own/available from your own company side, here your company former data/historical data plays an important role
i will send you a link for productivity, but use it for just comparison purpose
Best of luck