Building & Construction Production rates

Member for

16 years 3 months

there are rates at the top of this page for to determine installation durations. There are also standard estimating programs out there that will give you durations based on industry standards of installation i.e. X number of LF of large conduit installtion per day. Timberline (now SAGE), Richardson Race, Accu Bid, McCormik, Cubit, STACk, Turbobid, ProEst. 

Member for

8 years 5 months

Dear All,

Please send excel file for Manpower productivity for Building & construction projects in UAE,

my email ID, mubarakduke@gmail.com

Thanks,

Mubarak.s

Member for

19 years 10 months

Hi Mangesh

The prices are in £ but the production rates are pretty well universal.

Best regards

Mike Testro

Member for

14 years 7 months

Hello Mike...

Thanks for the info...I'll look for this..regards

Member for

18 years 6 months

Dear Mike,

 

Is the RICS estimating guide only meant for UK region?.

regards,

 

Mangesh Khuspe

Member for

14 years 6 months

Hello Mr Saju T.S can u forward me a copy / link for productivity

 

Thank you

Member for

19 years 10 months

Hi Ed

The RICS publish estimating books - also on CD - which have production outputs for construction work including M&E.

Other publications are Spons and also Hutchinson which you can order from Amazon.

Best regards

Mike Testro

Member for

14 years 11 months

Hi Saju,

Can you send me too the link for productivity?

Thank you,

SPP

 

Member for

14 years 7 months

thanks for the info.

Member for

16 years 4 months

Hi

Ed, Actually there is no such standard production rate, Its depends upon your company status regarding the Maximum number of labors, Machinery and cash.

For example, concrete road surfacing (300mm)-6.7 m2/hour,  But the important thing is whether your company can produce exact productivity? or some time your project team have high capacity to produce more?

unbalanced productivity can create  problems while setting duration and float.

 First of all you need to arrange all the activities  with in the contractual dates. from there you have to set the productivity then durations and links . you can consult the construction managers, site engineers, machines like excavator- there is a standard productivity, But the excavation rate depends upon the number of excavation machines own/available from your own company side, here your company  former data/historical data plays an important role

i will send you a link for productivity, but use it for just comparison purpose

Best of luck