Load Labor Units/ Manpower in an Updated Schedule

Member for

16 years 3 months

my answer reains that same 

add a resource to each activity and put in the budgeted units (manhours for each activity)

then just update your remaining manhours for activities that are in progress 

for your activiites that are completed update the reamining units as zero

Member for

15 years

Thanks for your valuable response!! But do we need to load the Manpower in all the activities including the completed ones. and what about the ongoing activities ?? we shall put only the remaining units or total units is also required to show a realistic Manpower Histogram !!

Thanks in advance!!

Member for

16 years 3 months

yes you can do it add a resource in the resource dictionary 

then add a resource to each activity and put in the budgeted units (manhours for each activity)

then just update your remaining manhours for activities that are in progress