Thanks for your valuable response!! But do we need to load the Manpower in all the activities including the completed ones. and what about the ongoing activities ?? we shall put only the remaining units or total units is also required to show a realistic Manpower Histogram !!
Thanks in advance!!
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2015-06-25 13:44
Member for
16 years 3 monthsmy answer reains that
my answer reains that same
add a resource to each activity and put in the budgeted units (manhours for each activity)
then just update your remaining manhours for activities that are in progress
for your activiites that are completed update the reamining units as zero
Member for
15 yearsThanks for your valuable
Thanks for your valuable response!! But do we need to load the Manpower in all the activities including the completed ones. and what about the ongoing activities ?? we shall put only the remaining units or total units is also required to show a realistic Manpower Histogram !!
Thanks in advance!!
Member for
16 years 3 monthsyes you can do it add a
yes you can do it add a resource in the resource dictionary
then add a resource to each activity and put in the budgeted units (manhours for each activity)
then just update your remaining manhours for activities that are in progress