Imprting baseline

Member for

18 years 1 month

Hi Selcuk.

I’m sure what I talking . :-)

After you reconfigure the option I presented, you create a new baseline in Maintain baseline function, and then assign the new baseline to Project BL and Primary BL.



Regards

Member for

18 years 5 months

Hi,



About Question 2: There are two steps to import a baseline. First step, maintain BL and second one is Assign BL as Project BL and also Primary user BL.

Are you sure that you realized these two steps?



Regards,

SE

Member for

18 years 1 month

Hi.

question 1 : There is BL Project start value in Date group. Usually it is identical to BL Project early start.

Member for

18 years 1 month

Hi.

question 2 : maybe you can try on changing this option. Goto Admin -> Preference -> Earned value -> in Earned value calculation , change value to "Budgeted value with current date"



Now create the baseline again and see whether the baseline date change.